• Info@rcssaar.com
  • +(202) 273 834 81-4
project Photo
project Photo
  • Customer : Owner: Princess Noura University Main contractor: Saudi Fressinet
  • Location : Riyadh-KSA
  • Duration : August/2011 – December/2011

Princess Noura University Metro

 Install and construct of 49 turnouts + insulated joints (slab track).
Thermite welding of rails & Destressing.

After sales service for shunter machine supplied by Zephir



project Photo
project Photo
  • Customer : Owner: SAR Main contractor: Yapi Merkezi
  • Location : Nariyah-KSA
  • Duration : June/2012 – January/2013

Track works in Nariyah SAR workshop

Install tracks inside Nariyah Workshop
(slab embedded tracks).

Installation of 2.4 track km , 100 thermite weldings , 451 track on plinth , and on  steel column 240 m 



project Photo
project Photo
  • Customer : Owner: SRO Main contractor: Al Mobty
  • Location : Riyadh – dammam KSA
  • Duration : November/2005 – April/2007

Renewal extension of sidings no 6 and 9 among main line no(1).

Construction of siding track works include supplying materials.   



project Photo
project Photo
project Photo
  • Customer : Owner: SAR Main contractor: Hyundai Engineering & Construction Co. Ltd.
  • Location : Ras El Kheir -KSA
  • Duration : March/2014 – March/2014

Special track Laying over bunker in Ras El Kheir , Maaden Alumina Refinery Project

Installations on steel beams in Ras El-Kheir, using weld in shoulders to fix rails.
Embeded tracks installations using special fixtures, adhustable jigs and plates.

Execute Alumino Thermic welding (300 Joint points)



project Photo
project Photo
  • Customer : Owner: SAR Main contractor: Barclay Mowlem
  • Location : From Riyadh to Dammam- KSA
  • Duration : January/2008 – July/2012

New Wagon Workshop Project

Construct of Gantry cranes tracks- Al Jouf Depot.

First and second tamping for 875 Km using RCS tamping 2 Machines.

Dynamic stabilization for 875 Km using RCS dynamic stabilizing machine.

Balast profiling for 600 KM using RCS ballast profiling machine.

Sweeping of the sand from all the CTW 300 tracks for the final hand over to SAR